Practice Test 4 | Google Cloud Certified Professional Cloud Network Engineer | Dumps | Mock Test

3,545

Your application team has developed a new application in GCP. The team needs a bandwidth of 40Gbps over dedicated interconnect for the application to be tested fully.

How many physical circuits are needed in the interconnect deployment?

A. 4
B. 5
C. 6
D. 7

Answer: A

Option A is correct, the dedicated interconnect is either in 10 Gbps or 100 Gbps increments

Option B, C & D is incorrect.

Reference: