A development team has implemented Azure Pipelines. They have defined an approval process based on a condition. There is a policy attached that the approvals must be completed within 5 hours.
But after implementation, the deployments start failing after 2 hours.
You need to ensure the deployments only fail if the approval time is longer than 5 hours.
You decide to modify the Time interval between the re-evaluation of gates from the Post-deployment conditions section.
Would this fulfill the requirement?
A. Yes
B. No
Answer – B
Gates are used to configure automated calls to external services. Since this is a manual approval, we should not work with the gate settings.